PRINCE2 PRINCE2-AGILE-PRACTITIONER RELIABLE DUMPS EBOOK - FREE SAMPLE PRINCE2-AGILE-PRACTITIONER QUESTIONS

PRINCE2 PRINCE2-Agile-Practitioner Reliable Dumps Ebook - Free Sample PRINCE2-Agile-Practitioner Questions

PRINCE2 PRINCE2-Agile-Practitioner Reliable Dumps Ebook - Free Sample PRINCE2-Agile-Practitioner Questions

Blog Article

Tags: PRINCE2-Agile-Practitioner Reliable Dumps Ebook, Free Sample PRINCE2-Agile-Practitioner Questions, Latest PRINCE2-Agile-Practitioner Exam Discount, New PRINCE2-Agile-Practitioner Test Price, PRINCE2-Agile-Practitioner Reliable Exam Practice

Web-based PRINCE2-Agile-Practitioner practice test of PrepAwayPDF is accessible from any place. You merely need an active internet connection to take this PRINCE2 PRINCE2-Agile-Practitioner practice exam. Browsers including MS Edge, Internet Explorer, Safari, Opera, Chrome, and Firefox support this PRINCE2-Agile-Practitioner Practice Exam. Additionally, this PRINCE2 Agile Practitioner Project Management Exam (PRINCE2-Agile-Practitioner) test is supported by operating systems including Android, Mac, iOS, Windows, and Linux.

If you are prepared to take the PRINCE2-Agile-Practitioner exam with the help of excellent PRINCE2-Agile-Practitioner learning materials on our website, the choice is made brilliant. Our PRINCE2-Agile-Practitioner training materials are your excellent choices, especially helpful for those who want to pass the PRINCE2-Agile-Practitioner Exam without bountiful time and eager to get through it successfully. Besides that, our PRINCE2-Agile-Practitioner study questions have three versions: PDF version, Soft version and APP version, which can be interestinng and helpful for you to choose.

>> PRINCE2 PRINCE2-Agile-Practitioner Reliable Dumps Ebook <<

Free Sample PRINCE2 PRINCE2-Agile-Practitioner Questions | Latest PRINCE2-Agile-Practitioner Exam Discount

Firstly, we can give you 100% pass rate guarantee on the PRINCE2-Agile-Practitioner exam. Our PRINCE2-Agile-Practitioner practice quiz is equipped with a simulated examination system with timing function, allowing you to examine your learning results at any time, keep checking for defects, and improve your strength. Secondly, during the period of using PRINCE2-Agile-Practitioner learning guide, we also provide you with 24 hours of free online services, which help to solve any problem for you on the PRINCE2-Agile-Practitioner exam questions at any time and sometimes mean a lot to our customers.

PRINCE2 PRINCE2-Agile-Practitioner Exam Syllabus Topics:

TopicDetails
Topic 1
  • Project Management Solution: This domain is aimed at PRINCE2 Agile Practitioners and highlights the importance of a complete project management solution. It emphasizes the synergy between agile flexibility and the structured framework of PRINCE2.
Topic 2
  • PRINCE2 Agile® Practitioner Overview: This section of the exam measures the skills of PRINCE2 Project Managers and covers the integration of PRINCE2 and Agile methodologies. Candidates will learn how to effectively combine these approaches to create a comprehensive project management solution that balances control with flexibility.
Topic 3
  • Skills and Processes: This section measures the capabilities of PRINCE2 Project Managers in utilizing best practice guidance for project delivery. It focuses on equipping professionals with the necessary skills to manage projects effectively in fast-paced environments.
Topic 4
  • Certification Validity: This section informs candidates about the certification's validity period, which is three years for PRINCE2 Agile Practitioner holders. The emphasis is on maintaining certification through either re-sitting the exam or engaging in AXELOS membership activities.
Topic 5
  • Target Audience: This domain is designed for professionals working in project environments, particularly those responsible for integrating project management with product delivery. It outlines the certification's relevance for individuals looking to enhance their project management capabilities while maintaining governance and control.

PRINCE2 Agile Practitioner Project Management Exam Sample Questions (Q36-Q41):

NEW QUESTION # 36
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
In order to assess the prevailing agile environment, the project manager made use of the Agilometer. A summary of the results from canvassing the views of key stakeholders involved in the Event Village is provided below:
Slider
Flexibility on what is delivered:Score 5
Level of Collaboration:Score 2
Ease of Communication:Score 3
Ability to work iteratively and deliver incrementally:Score 4
Advantageous Environmental Conditions:Score 5
Acceptance of Agile:Score 3
Which observation is appropriate at this point?

  • A. There is a need to investigate if team members have been disappointed by working in teams before.
  • B. There is a need to evolve the Agilometer to better suit the needs of the project manager.
  • C. There are likely to be too many requirements that are 'Musts Haves' to be able to use PRINCE2 Agile.
  • D. The average score supports adopting Agile behaviours, concepts and techniques.

Answer: D

Explanation:
The scores indicate a mixed but generally positive view of the agile environment, with certain areas like flexibility and advantageous conditions scoring well. While collaboration and communication could improve, the overall results suggest that there is a foundation for adopting Agile behaviors, concepts, and techniques within the project. This supports the notion of continuing with agile practices while focusing on areas that need enhancement.


NEW QUESTION # 37
Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?

  • A. To allow teams to self-organize whilst staying in control.
  • B. To adjust a 'command and control' culture for product delivery.
  • C. PRINCE2 Agile is NOT a substitute for PRINCE2.
  • D. Projects should be established with the intention of NOT delivering everything.

Answer: A

Explanation:
This approach enables teams to adopt Agile practices while maintaining the governance and structure provided by PRINCE2, promoting both flexibility and control in project delivery.


NEW QUESTION # 38
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre oftown has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The following assessment was made initially during the 'starting up a project' process:
'The Website Team is already using Scrum and it is expected that this team will be familiar with agile techniques. However, the Staff Training Team is less familiar with the agile ways of working.' Training on agile techniques was given to the Staff Training Team as a result of this assessment.
As part of the 'closing a project" process, the following observation was made:
'The Staff Training Team gained more understanding of what to fix and what to flex as the project moved into Stage 3.' Why should this observation appear in the end project report?

  • A. The end project report should sum up the results of each timebox and stage.
  • B. The end project report should review how much scope was delivered by the project.
  • C. The end project report should review the use of the Agilometer and the agile ways of working.
  • D. The end project report should hand over the remaining Could Haves to operational staff.

Answer: C

Explanation:
This observation highlights the Staff Training Team's improved understanding of agile methodologies as the project progressed, which is relevant to evaluating the effectiveness of the training provided and how well the team adapted to agile practices. Including this in the end project report emphasizes the project's contribution to developing agile capabilities within the organization.


NEW QUESTION # 39
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
During the 'initiating a project' process, the project manager has decided to use the Cynefin framework to assess the project.
As a result, the following observation was made as part of the assessment:
'There is a relationship between the social media websites promoting active lifestyles and participation in sport. This in turn leads to an increase in the health and fitness of the people.
It will not be possible to measure the effect of the social media websites until after the project. The results of early communications on the websites should be reviewed in order to identify what effect it may be having, and why. This will then feed into further longer term initiatives at the LGA.' How should this relationship be assessed according to the Cynefin framework?

  • A. Chaotic
  • B. Complex.
  • C. Obvious.
  • D. Disorder

Answer: B

Explanation:
In the complex domain, cause-and-effect relationships are not immediately apparent and can only be understood in retrospect. The relationship between social media websites promoting active lifestyles and their effect on health and fitness is not straightforward, as it involves multiple interacting factors. Since it will not be possible to measure the impact until after the project, the focus should be on observing and analyzing early communications and their effects. This aligns with the Cynefin framework's recommendation to probe, sense, and respond, allowing for adaptive management based on feedback and insights gained throughout the project.


NEW QUESTION # 40
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The project manager recommends that Stage 2 should be broken down further with more stage boundaries linked to the weekly publication of a newspaper advertisement.
Using the Timeline, which statement BEST evaluates this proposal in relation to the 'manage by stages' principle?

  • A. It applies the principle poorly because stage boundaries should be set at the beginning of each new timebox.
  • B. It applies the principle well because short stage boundaries provide more opportunity for inter-team collaboration.
  • C. It applies the principle poorly because the stage boundaries should typically be monthly on a three- month project.
  • D. It applies the principle well because short stage boundaries will enable the project to fail-fast and learn- fast.

Answer: D

Explanation:
The 'manage by stages' principle emphasizes breaking the project into manageable stages to assess progress and adapt as necessary. By creating shorter stage boundaries linked to the weekly publication of advertisements, the project can quickly identify issues and adjust strategies, fostering a learn-fast approach.


NEW QUESTION # 41
......

As the saying goes, knowledge has no limits. You may be old but the spirit of endless learning won't be old. If you attend the test of PRINCE2-Agile-Practitioner certification you will update your stocks of knowledge and improve your actual abilities, buying our PRINCE2-Agile-Practitioner exam practice materials can help you pass the test smoothly. There are no threshold limits to attend the PRINCE2-Agile-Practitioner test such as the age, sexuality, education background and your job conditions, and anybody who wishes to improve their volume of knowledge and actual abilities can attend the PRINCE2-Agile-Practitioner test.

Free Sample PRINCE2-Agile-Practitioner Questions: https://www.prepawaypdf.com/PRINCE2/PRINCE2-Agile-Practitioner-practice-exam-dumps.html